There are three things extremely hard: steel, a diamond, and to know one’s self - I am proud of just this mile of steel upon it, my visions come to life - A warrior's word is unchanging as steel - My heart is true as steel - The finest steel has to go through the hottest fire - The same hammer that shatters glass forges the steel - The most beautiful bridge in the world so pure, so resolute, so regular that here finally, steel architecture seems to laugh - Hit the Iron when still hot! - Only Iron cuts Iron - Can I fear... when life is but trivial, and a heart of steel and blazing fire!
Home
- Preface
- Management Principle
- Message
Project
- Status
- Summary
- Phase I
- Phase II
- Partners
- Location
Contact Us
Project Status
TECHNOLOGICAL CONSULTANT - SIEMENS METAL TECHNOLOGIES / VOEST ALPINE / FUCHS / POMINI
Under contract with ASI for complete Turn key supply, supervision, commissioning and Start up of plant.
ADMINISTRATIVE CONSULTANT- ERNST & YOUNG CONSULTING,
Under contract with ASI for complete plant Policies & procedures. Documentation delivered.
PMC CONSULTANT - VWN STEEL SOLUTIONS, SWITZERLAND
Under contract with ASI for complete engineering approval, supervision, commissioning & start up of plant.
CIVIL CONSULTANT – YUSSUF BAASHEN CONSULTANTS
Under contract with ASI for site civil works supervision
SOIL CONTRACT – AL NAFAI CONTRACTING, YANBU
Under contract for soil improvement. Filling, leveling, and compacting.
SAUDI INDUSTRIAL DEVELOPMENT FUND
- Contract in Force for industrial Loan.
CONTRACT WITH SIEMENS VAI: –IN FORCE
1. Basic design – Completed
2. Basic Engineering – Completed
3. Detailed Engineering – 95% Completed
4. Inquiry & Specifications – Completed
5. Manufacturing order release – In progress
PROJECT SITE:
1. Site lease Contract with Royal Commission of Yanbu signed.
2. Work Permit issued and site taken over by ASI.
3. Site soil improvement completed in 3 months.
4. Site leveling, compaction and finishing in progress.
PROJECT UTILITIES:
1. Power allocation contract with MARAFIQ signed.
2. Utility contract with MARAFIQ signed.
3. Natural Gas from ARAMCO, allocation agreement signed.
4. Environmental clearance obtained.
5. Approval from Ministry of safety and security obtained.
CIVIL WORKS:
1. Civil Contractors shortlisted
2. Civil contract ready for signature
3. Site under preparation for handing over to Contractor for Civil works.
4. Work to begin after HAJJ .
PROJECT COMMISSIONING:
1. Cold commissioning to start by First Quarter 2013
2. Hot Commissioning to start by Second Quarter 2013
3. Commercial production to start by Second Quarter 2013